Woodstock Exchange

Woodstock Exchange

Project Duration: November 2015 – February 2016Value: ZAR 2 million / USD 145 000Brief: Back Up Power / Energy ConsciousAlternator : Site voltage 400V : 400V directA 700kVA UK Perkins generator set, housed in a soundattenuated / weather proof canopy

superwattadmin May 10, 2017April 3, 2019 Projects Read more

Cape Town Train Station

Cape Town Train Station

Project Duration: July 2009 – October 2010Value: ZAR 7 million / USD 500 000Brief: Cogeneration / Back Up PowerAlternator : Site voltage 400V : 400V (including 3.3kV step-up step-down transmission)Providing a complete overhaul of Cape Town Station’s back-up electricity supply

superwattadmin May 10, 2017April 3, 2019 Projects Read more

Cape Town Film Studios

Cape Town Film Studios

Project Duration: February 2010 – August 2010Value: ZAR 3 million / USD 214 000Brief: Back Up Power/MV switchgear control / Sound SensitiveAlternator : Site voltage 400V : 11kVA synchronised 2x 500kVA system with 11kV step-up into the site’s 11kV MV

superwattadmin May 10, 2017April 3, 2019 Projects Read more

Gastro Foods

Gastro Foods

Project Duration: January 2015 – May 2015Value: ZAR 4 million / USD 290 000Brief: MV switchgear control/Back UpAlternator : Site voltage 400V : 11kVSWT installed a 1.65MVA standby diesel generator, able to deliver 1320KW of power. The 12 cylinder Perkins

superwattadmin May 10, 2017April 3, 2019 Projects Read more

Areva Resources & Uramin Namibia, Trekkopje Desalination Project

Areva Resources & Uramin Namibia, Trekkopje Desalination Project

Project Duration: July 2009 – December 2009Value: ZAR 21 million / USD 1.5 millionBrief: Cogeneration /Substation control/ Back Up Power / Relocated SiteAlternator : Site voltage 400V : 33kVSupplying Uramin Namibia (Pty) Ltd – part of the French Nuclear giant

superwattadmin May 10, 2017April 3, 2019 Projects Read more

AMC – North Africa

AMC – North Africa

Project Duration: April 2014 – February 2016 (phase 1)Value: ZAR 200 million / USD 14.3 millionBrief: Full Infrastructure / Continuous PowerAlternator : Site voltage 690V : 33kVEngineering, procurement and construction of a power plant, complete with bulk diesel (1500kl) and

superwattadmin May 10, 2017April 3, 2019 Projects Read more

Nampak Products Limited (trading as DivFood)

Nampak Products Limited (trading as DivFood)

Project Duration: May 2015 – March 2016Value: ZAR 50 million / USD 3.6 millionBrief: Cogeneration /MV switchgear control/ Back Up PowerAlternator : Site voltage 400V : 11kV (400V direct in Paarl)Providing modular backup power solutions to Nampak’s largest packaging production

superwattadmin May 10, 2017April 3, 2019 Projects Read more

Swakop Uranium – Husab Project

Swakop Uranium – Husab Project

(World’s 2nd Largest Uranium Mine, Namibia)Project Duration: October 2014 – June 2016Value: ZAR 70 million / USD 5 millionBrief: Full Infrastructure /Cogeneration / Substation control/ Back Up PowerAlternator : Site voltage 400V : 33kVEngineering, procurement and construction of a standby

superwattadmin May 9, 2017April 3, 2019 Projects Read more

Suite 7, Steenberg House

Steenberg Office Park

8 Silverwood Close

Tokai 7945

Tel: +27 (0) 21 709 8200

Fax: +27 (0) 21 709 8201

General enquiries: [email protected]

Copyright © 2026 Superwatt Power Solutions. All rights reserved. Theme Spacious by ThemeGrill. Powered by: WordPress.